Skip to content

Defence and aerospace manufacturing · Llangeinor, Bridgend

637 kW Rooftop Solar: Irvin-GQ, South Wales | FLD

Commercial rooftop solar PV across two large roof elevations: structural feasibility survey, Valk flat-roof ballast system design, NGED G99 connection, five Solis 110 kW Pro three-phase inverters, dedicated 415V distribution, remote monitoring, commissioning and aftercare.

Client
Irvin-GQ Limited
Location
Llangeinor, Bridgend
Project value
£525,000
Completed
September 2025
System size
637 kW
Annual generation
1,076,078 kWh site consumption offset — building runs off-grid at peak generation
Annual saving
Lifetime ROI £3 million
Payback period
3 years
Irvin-GQ main roof solar array — 637 kW commercial installation, Bridgend

Main roof elevation with Valk ballast-mounted panels

Irvin-GQ second roof elevation solar panels, Llangeinor

Second roof elevation — Solis 110 kW inverter string

The challenge

The challenge

Irvin-GQ is a defence and aerospace manufacturer supplying parachute and aerial-delivery systems into Ministry of Defence and NATO programmes. The facility runs a continuous daytime production load with precision sewing, testing rigs and compressed-air plant across two shifts — total annual site consumption of 1,076,078 kWh. Two constraints shaped the brief. First, the buildings carry two large roof elevations of differing construction, which meant the ballast and panel layout had to be engineered per elevation rather than applied as a single blanket design. Second, the customer had a board-level deadline aligned to financial year-end and a Scope 3 reporting commitment cascading from their MoD customer base, so the project could not slip.

Our solution

Our solution

FLD ran a full structural feasibility survey on both roof elevations before finalising the layout. A Valk flat-roof ballast mounting system was specified so panels sit securely without roof penetrations, preserving the existing waterproofing. The full 637 kW array was distributed across the two elevations to maximise yield without overloading either roof. Five Solis 110 kW Pro commercial three-phase inverters were installed in a dedicated plant room with 415V distribution, fault protection and remote monitoring. A G99 application was coordinated with NGED in parallel with procurement, compressing the overall lead time. Installation was phased so production was never stopped. A single NICEIC Approved Contractor sign-off covered the complete installation.

The result

The result

At peak generation the building runs fully off-grid against a premises consumption of 1,076,017 kWh per year. Annual CO2 saving of 441.632 tonnes — 14,800 trees-equivalent. Payback 3 years, lifetime ROI £3 million. The client has since commissioned FLD to scope battery storage addition to capture afternoon surplus against overnight site load, and is progressing with Scope 3 reporting integration into their MoD supply-chain disclosures.

Related service
Commercial Solar PV Installation in South Wales

Factory, warehouse and commercial rooftop solar from 30 kWp to 1 MW across Swansea, Cardiff, Newport, Pembrokeshire and the wider South Wales region.

Learn more
Similar project?

Discuss a scheme like 637 kW Rooftop Solar: Irvin-GQ, South Wales | FLD

Send us the outline of your site and we will come back within one working day with a feasibility view and an honest lead time.

Ready for a fixed-price quotation?

Speak to Paul directly. Most quotes turn around within five working days of a site survey.

Trusted by NHS care providers, HMCTS and private developers across South Wales.