Rainbow Leisure Centre — electrical refurbishment and lighting

Full electrical refurbishment across the leisure centre estate: LV distribution upgrade, high-bay LED lighting to sports halls and pool hall, emergency lighting to BS 5266, fire alarm interfacing to BS 5839, power and data for reception and gym zones, poolside IP-rated fittings, and handover commissioning.

Client
Rainbow Leisure Centre operator
Location
South Wales
Project value
approximately £75,000
Completed
November 2025
Pool hall with overhead IP-rated LED lighting at a UK leisure centre

Pool hall IP-rated LED lighting commissioned to BS 7671 Section 702

Sports hall interior with high-bay LED lighting

Sports hall high-bay LED — uniform illuminance and glare control

Gym interior with overhead lighting and power points
Leisure centre reception and foyer lighting
The challenge

The challenge

Leisure centres are among the more difficult electrical environments we work in. Sports halls demand high uniform illuminance with very strict glare control for broadcast-grade and club-competition use. Pool halls layer humidity and chlorine exposure on top, requiring IP-rated fittings throughout and strict bonding compliance. On top of that, the operator needed the centre to remain open for member sessions across the refurbishment window — scaffolded out-of-hours working only, with life-safety systems live across every changeover.

Our solution

Our solution

FLD staged the works across pool, sports hall, gym and reception zones so that only one zone was offline at a time. High-bay LED fittings were specified with the appropriate beam angles and colour temperature for sports-hall use and with IP-rated equivalents for the pool hall, bonded to the pool equipotential network per BS 7671 Section 702. Emergency lighting was designed to BS 5266 with three-hour duration on the full escape route and tested at commissioning. Fire alarm interfacing was coordinated with the existing BS 5839 panel so that no detection zone went offline across the programme. A single NICEIC Approved Contractor sign-off covered the whole scope.

The result

The result

The centre stayed open for members throughout the refurbishment, with measured illuminance up across every sports and pool zone and materially reduced electrical running costs through the LED conversion. The emergency lighting and fire alarm certification were accepted by the operator's insurers on first submission.

Related service
Commercial Electrical Contractors in South Wales

Complete commercial electrical scope for offices, retail units and commercial premises. Reference project: Cardiff Crown Courts refurbishment.

Learn more
Similar project?

Discuss a scheme like Rainbow Leisure Centre

Send us the outline of your site and we will come back within one working day with a feasibility view and an honest lead time.

Ready for a fixed-price quotation?

Speak to Paul directly. Most quotes turn around within five working days of a site survey.

Trusted by NHS care providers, HMCTS and private developers across South Wales.