Cardiff is the capital of Wales, with a 2021 census population of 362,756 and the largest commercial office estate in the principality. Major employers concentrated inside the central business district include Admiral Group with its FTSE 100 headquarters at Capital Tower, Legal and General, the BBC Cymru Wales headquarters at Central Square, Principality Building Society, NHS Wales at the University Hospital of Wales, Cardiff University, and the Motorpoint Arena Cardiff.

PVGIS modelling for CF10 returns typical annual yields of around 940 kWh per kWp installed for a well-oriented rooftop array at 30 to 35 degrees pitch. In practice that means a 4 kWp domestic array generates roughly 3,760 kWh per year, and a 50 kWp commercial rooftop around 47,000 kWh.

Commercial solar in Cardiff

Densest commercial office-roof stock in Wales with MEES B-by-2030 driving demand. For commercial operators, the combination of a predictable 940 kWh/kWp yield, current commercial electricity prices at 28 to 32p per kWh, and the Annual Investment Allowance tax treatment means simple payback on a well-sized Cardiff commercial array typically lands between 3.5 and 6 years.

Worked example: 100 kWp commercial installation

Typical Cardiff commercial rooftops

We have installed commercial solar across Capital Waterside, Cardiff Central Enterprise Zone, Cardiff Business Park Llanishen and other industrial estates in Cardiff. Typical system sizes range from 30 kWp on smaller trade units to 500 kWp-plus on larger warehouse and factory roofs.

Domestic solar in Cardiff

For Cardiff homeowners, a typical domestic installation is a 4 to 5 kWp array paired with a 5 to 10 kWh battery. At 940 kWh/kWp, a 4 kWp system generates around 3,760 kWh in year one, which covers a meaningful share of a three or four-bedroom household's annual consumption once battery storage smooths the time-of-use mismatch. Payback typically lands at 7 to 10 years at current pricing and Smart Export Guarantee tariffs.

Planning and grid connection

The planning authority for Cardiff is Cardiff Council. Rooftop solar PV on commercial buildings almost always falls within permitted development under the Town and Country Planning (General Permitted Development) (Wales) Order, subject to the usual 200 mm projection limit and non-listed, non-scheduled-monument conditions. Properties inside a conservation area will typically require full planning permission; we handle the application end-to-end.

For grid connection, systems above 3.68 kW per phase require a G99 application to the DNO. Typical approval timelines are 6 to 8 weeks for Type A (up to 1 MW), which we lodge concurrently with design and procurement so they do not sit on the critical path.

Why FLD for your Cardiff installation

Start the conversation

If you own a commercial rooftop or a domestic property in Cardiff (CF10, CF24, CF11) and want a realistic assessment against your actual consumption data, call Paul direct on 01792 680611 or visit our Cardiff location page for full local detail.

FAQ

Frequently asked questions

A Power Purchase Agreement is a financing arrangement where we fund and install a rooftop solar system at no upfront cost. Your business buys the electricity the system generates at a fixed, RPI-indexed rate that is lower than your grid tariff. The PPA typically runs 10 to 25 years. At the end you can extend, buy out at a pre-agreed residual value, or have the system removed. It suits businesses that want immediate savings without capital outlay and that are credit-worthy with a stable site.
At 30p/kWh grid electricity, a 100 kWp system generating 95,000 kWh/yr with 70% self-consumption delivers around £24,000 of year-one benefit against c. £85,000 capex, a 3.5-year simple payback. Under Annual Investment Allowance first-year 100% relief, post-tax payback is closer to 2.6 years. South Wales yields 940 to 985 kWh/kWp/year depending on postcode, comfortably enough for commercial solar to be cashflow positive from month one with a PPA.
NICEIC is the UK's most recognised certification body for electrical installers. An NICEIC Approved Contractor has been audited on competence, quality management and BS 7671 compliance. It gives you an insurance-backed warranty on the installation work we sign off, and meets the Competent Person scheme requirements for Building Regulations Part P.
Yes, depending on organisation type. Welsh SMEs and public bodies can access the Welsh Government Energy Service, Ynni Cymru Capital Grants (approximately £10 m in 2026-27, £25,000 to £1 m per project) and Development Bank of Wales Green Business Loans. Welsh public-sector bodies use Salix Wales Funding Programme rather than the English Public Sector Decarbonisation Scheme. Farms may be eligible under Farming Connect. Always check current-year terms before committing.

Ready for a fixed-price quotation?

Speak to Paul directly. Most quotes turn around within five working days of a site survey.

Trusted by NHS care providers, HMCTS and private developers across South Wales.